Critical Breakthrough in the Approval Process of Shunde Ronggui Project
Addtime:2015-07-15 Hits:226

NORINCO Real Estate won the bidding for Shunde Ronggui Tract on September 18, 2014. The subsidiary project company was later founded on December 16. The newborn project company faced many challenges. Besides staff shortages, tight time constraints and heavy workload, they must manage to avoid the adverse impact of the upcoming project approval reform in Shunde District as well as the new national fire regulations which will be implemented on May 1, 2015. The policy changes will make the project approval process more complex and time consuming.

To ensure that the construction work begins on time, the project company and the headquarters cooperated closely and made great efforts to speed up the project approval process. Finally, the project was granted all the construction permits and received the professional examination advice on civil air defense, water and soil conservation, lightning protection and working drawing review before April 29, 2015. These critical work laid a good foundation for achieving the goal of starting the construction work in the second half of 2015.

According to the approved design, the basement ceiling height is limited. As a result, the underground area for civil air defense is reduced, saving the cost of the project. The fire control design was also approved before the implementation of the new national fire regulations, increasing 2600 square meters salable area. The project company’s efforts to achieve maximum efficiency are ultimately rewarded.

 


NORINCO Real Estate (Foshan Shunde) Co., Ltd.